Shell Beach Road Streetscape Project

Shell Beach Streetscape Banner
  1. Current Events
  2. Project Information

Current Events

On June 19, 2018 the City Council unanimously approved the Shell Beach Streetscape project. The contractor is John Madonna Construction Co., Inc. and construction is scheduled to begin in late August. A project kick-off celebration was held on Friday, August 24, 2018.

A tentative construction schedule is below. This information will be updated often, so check back frequently.

Updated as of 2/6/2020

 Start Date  End Date  Location Activity
2/10/20 2/12/20 Shell Beach Rd, Morro to Palomar Demo concrete, pour light pole bases, install irrigation lines, install electric lines, pour curb and gutter
2/13/20  2/14/20 Shell Beach Rd, Windward to Boaker Demo and rough grade
2/13/20 2/14/20 Shell Beach Rd, Morro to Montecito Rough grade and base grade
2/14/20 2/14/20 Shell Beach Rd, Montecito to Palomar Grade for sidewalk
2/17/20 2/17/20   No Work - President's Day Holiday
2/18/20  2/19/20 Shell Beach Rd, Pier to Leeward Demo and pour retaining curb at Village Pottery. Demo planter and rebuild at Shell Beach Inn
2/20/20 2/21/20 Shell Beach Rd, Pier to Leeward  Prep for sidewalk at Village Pottery. Demo and sidewalk subgrade at Shell Beach Liquor
 2/24/20 2/28/20 Shell Beach Rd, Boeker to Placentia Demo, prep subgrade, irrigation and electrical lines, pour pole bases and curb and gutter
2/27/20  2/28/20 Shell Beach Rd, Windward to Boeker Pour concrete