Shell Beach Road Streetscape Project

Shell Beach Streetscape Banner
  1. Current Events
  2. Project Information

Current Events

On June 19, 2018 the City Council unamiously approved the Shell Beach Streetscape project. The contractor is John Madonna Construction Co., Inc. and construction is scheduled to begin in late August. A project kick-off celebration was held on Friday, August 24, 2018.

A tentative construction schedule is below. This information will be updated often, so check back frequently.

Updated as of 9/19/19

**The contractor is completing the rough grading for the future curb and gutter and multi-use path on Shell Beach Rd. along the Caltrans side from Cliff Ave. to Esparto Ave. During this time parking will be very limited due to the need to protect those graded areas. The concrete curb and gutter has been poured. This will allow the road striping to be re-painted into straight traffic lanes and parking along the Caltrans side of Shell Beach Rd. will be restored on September 27th. We appreciate your continued patience!

 Start Date  End Date  Location Activity
8/21/19  10/24/19 Shell Beach Road - Cliff to Terrace PG&E installing wire
8/21/19 11/12/19 1465 Shell Beach Rd  Parking lot construction
8/21/19 10/14/19 Shell Beach Rd at Windward Storm drain construction
8/21/19  10/1/19 Shell Beach Rd at Esparto Storm drain construction
9/10/19 9/27/19 Shell Beach Rd - Cliff to Terrace Install curb along Caltrans fence for multi-use path